Q. A can complete a work in 45 days. After working for 15 days, the remaining work is:
β
Correct Answer: (B)
2/3
Explanation: Completed = 15/45 = 1/3. Remaining = 2/3.
Explanation by: Deepak Sahoo
Completed = 15/45 = 1/3. Remaining = 2/3.