Q. A can complete a work in 18 days and B in 24 days. In how many days can they complete the work together?

  • (A) 10 days
  • (B) 10.29 days
  • (C) 10.8 days
  • (D) 12 days
βœ… Correct Answer: (B) 10.29 days
Explanation: Combined rate = 1/18 + 1/24 = 7/72. Time = 72/7 = 10.29 days.
Explanation by: Deepak Sahoo
Combined rate = 1/18 + 1/24 = 7/72. Time = 72/7 = 10.29 days.