Q. A can complete 3/8 of a work in 9 days. How many days will A take to complete the whole work?

  • (A) 20 days
  • (B) 22 days
  • (C) 24 days
  • (D) 26 days
βœ… Correct Answer: (C) 24 days
Explanation: Whole work = 9 × 8/3 = 24 days.
Explanation by: Deepak Sahoo
Whole work = 9 × 8/3 = 24 days.