Q. A completes a work in 30 days and B in 45 days. If both work together for 9 days, what fraction of the work remains?

  • (A) 1/5
  • (B) 1/2
  • (C) 3/5
  • (D) 4/5
βœ… Correct Answer: (B) 1/2
Explanation: Combined rate = 1/18. In 9 days completed = 1/2. Remaining = 1/2.
Explanation by: Deepak Sahoo
Combined rate = 1/18. In 9 days completed = 1/2. Remaining = 1/2.