Q. A is 20% more efficient than B. If B takes 30 days to complete a work, A will take:

  • (A) 24 days
  • (B) 25 days
  • (C) 26 days
  • (D) 28 days
βœ… Correct Answer: (B) 25 days
Explanation: Time = 30/1.2 = 25 days.
Explanation by: Deepak Sahoo
Time = 30/1.2 = 25 days.

πŸ“ Notes by Other Students/ Teachers


πŸ“Š Question Analytics

πŸ‘οΈ
22
Total Visits
πŸ“½οΈ
2 mo ago
Published
πŸŽ–οΈ
Deepak Sahoo
Publisher
πŸ“ˆ
88%
Success Rate