Q. A is 20% more efficient than B. If B takes 30 days to complete a work, A will take:
β
Correct Answer: (B)
25 days
Explanation: Time = 30/1.2 = 25 days.
Explanation by: Deepak Sahoo
Time = 30/1.2 = 25 days.