Q. A is 20% more efficient than B. If B takes 30 days to complete a work, A will take:

  • (A) 24 days
  • (B) 25 days
  • (C) 26 days
  • (D) 28 days
βœ… Correct Answer: (B) 25 days
Explanation: Time = 30/1.2 = 25 days.
Explanation by: Deepak Sahoo
Time = 30/1.2 = 25 days.