Q. A can complete a work in 15 days and B in 20 days. They work together for 4 days after which B leaves. The remaining work will be completed by A in:

  • (A) 7 days
  • (B) 8 days
  • (C) 9 days
  • (D) 10 days
βœ… Correct Answer: (B) 8 days
Explanation: Completed in 4 days = 4 × (7/60) = 7/15. Remaining = 8/15. A finishes in (8/15) × 15 = 8 days.
Explanation by: Deepak Sahoo
Completed in 4 days = 4 × (7/60) = 7/15. Remaining = 8/15. A finishes in (8/15) × 15 = 8 days.