Q. A can complete a work in 40 days and B in 60 days. They work alternately starting with A. In how many days will the work be completed?

  • (A) 47 days
  • (B) 48 days
  • (C) 49 days
  • (D) 50 days
βœ… Correct Answer: (B) 48 days
Explanation: In 2 days they complete 1/40 + 1/60 = 1/24. After 24 pairs (48 days), work is completed.
Explanation by: Deepak Sahoo
In 2 days they complete 1/40 + 1/60 = 1/24. After 24 pairs (48 days), work is completed.