Q. A can do a piece of work in 24 days. B is 50% more efficient than A. In how many days can B complete the work?

  • (A) 12 days
  • (B) 16 days
  • (C) 18 days
  • (D) 36 days
βœ… Correct Answer: (B) 16 days
Explanation: B's efficiency = 150% of A's efficiency. Time taken by B = 24/1.5 = 16 days.
Explanation by: Krishna Sharma
B's efficiency = 150% of A's efficiency. Time taken by B = 24/1.5 = 16 days.