Q. A is twice as efficient as B. If B can complete a work in 24 days, in how many days can A complete it?

  • (A) 8 days
  • (B) 12 days
  • (C) 16 days
  • (D) 48 days
βœ… Correct Answer: (B) 12 days
Explanation: A is twice as efficient, so A takes half the time taken by B = 24/2 = 12 days.
Explanation by: Krishna Sharma
A is twice as efficient, so A takes half the time taken by B = 24/2 = 12 days.