Q. A can complete a work in 18 days and B in 24 days. They work together for 6 days. What fraction of the work is completed?

  • (A) 1/2
  • (B) 7/12
  • (C) 5/8
  • (D) 3/4
βœ… Correct Answer: (B) 7/12
Explanation: Combined 1-day work = 1/18 + 1/24 = 7/72. In 6 days, work completed = 42/72 = 7/12. Therefore, option2 is correct.
Explanation by: Krishna Sharma
Combined 1-day work = 1/18 + 1/24 = 7/72. In 6 days, work completed = 42/72 = 7/12. Therefore, option2 is correct.

πŸ’¬ Discussion


πŸ“Š Question Analytics

πŸ‘οΈ
1
Total Visits
πŸ“½οΈ
10 h ago
Published
πŸŽ–οΈ
Krishna Sharma
Publisher
πŸ“ˆ
89%
Success Rate