Q. A and B can complete a work in 18 days, B and C in 24 days, and C and A in 36 days. In how many days can A, B and C together complete the work?

  • (A) 12 days
  • (B) 14 2/5 days
  • (C) 16 days
  • (D) 18 days
βœ… Correct Answer: (C) 16 days
Explanation: Adding pairwise rates: 2(A+B+C) = 1/18 + 1/24 + 1/36 = 1/8. Thus, A+B+C = 1/16, so they take 16 days. Therefore, option3 is correct.
Explanation by: Krishna Sharma
Adding pairwise rates: 2(A+B+C) = 1/18 + 1/24 + 1/36 = 1/8. Thus, A+B+C = 1/16, so they take 16 days. Therefore, option3 is correct.