Q. Consider a project with a first cost (investment) of $250,000, an annual O&M cost of $50,000, annual revenue of $160,000, and a salvage value of $40,000 after a 10-year life. Find the annual worth of the project assuming an interest of 13% per year.
✅ Correct Answer: (D)
66099