Q. A big advantage of PERT over Gantt charts is that in the former case
  • (A) activities and events are clearly shown
  • (B) early start and late finish of an acยฌtivity are clearly marked
  • (C) activity times are clear
  • (D) inter-relationship among activities is clearly shown.
๐Ÿ’ฌ Discuss
โœ… Correct Answer: (D) inter-relationship among activities is clearly shown.