Q. A 66.6% risk is considered as
  • (A) very low
  • (B) low
  • (C) moderate
  • (D) high
πŸ’¬ Discuss
βœ… Correct Answer: (D) high

Explanation: the probability of the risk might be assessed as very low (<10%), low (10–25%), moderate (25–50%), high (50–


Explanation by: Mr. Dubey
the probability of the risk might be assessed as very low (<10%), low (10–25%), moderate (25–50%), high (50–