Q. What describes the data and control to be processed?
  • (A) planning process
  • (B) software scope
  • (C) external hardware
  • (D) project complexity
πŸ’¬ Discuss
βœ… Correct Answer: (B) software scope

Explanation: functions described in the statement of scope are evaluated and in some cases refined to provide more detail prior to the beginning of estimation.


Explanation by: Mr. Dubey
functions described in the statement of scope are evaluated and in some cases refined to provide more detail prior to the beginning of estimation.