Q. A is developed using historical cost information that relates some software metric to the project cost.
  • (A) algorithmic cost modelling
  • (B) expert judgement
  • (C) estimation by analogy
  • (D) parkinson’s law
๐Ÿ’ฌ Discuss
โœ… Correct Answer: (A) algorithmic cost modelling

Explanation: the model uses a basic regression formula with parameters that are derived from historical project data and current as well as future project characteristics.


Explanation by: Mr. Dubey
the model uses a basic regression formula with parameters that are derived from historical project data and current as well as future project characteristics.