Q. It is often difficult to estimate size at an early stage in a project when only a specification is available
  • (A) true
  • (B) false
  • (C) ---
  • (D) ---
πŸ’¬ Discuss
βœ… Correct Answer: (A) true

Explanation: function-point and object-point estimates are easier to produce than estimates of code size but are often still inaccurate.


Explanation by: Mr. Dubey
function-point and object-point estimates are easier to produce than estimates of code size but are often still inaccurate.