Q. Which technique is applicable when other projects in the same analogy application domain have been completed?
  • (A) algorithmic cost modelling
  • (B) expert judgement
  • (C) estimation by analogy
  • (D) parkinson’s law
πŸ’¬ Discuss
βœ… Correct Answer: (C) estimation by analogy

Explanation: the cost of a new project is estimated by analogy with these completed projects.


Explanation by: Mr. Dubey
the cost of a new project is estimated by analogy with these completed projects.