Q. In a network, a critical path is the time- wise shortest path.
  • (A) true
  • (B) false
  • (C) ---
  • (D) ---
πŸ’¬ Discuss
βœ… Correct Answer: (B) false

Explanation: in a network, a critical path is the time-wise longest path. the critical path in the critical path method plays an essential role in scheduling and planning.


Explanation by: Mr. Dubey
in a network, a critical path is the time-wise longest path. the critical path in the critical path method plays an essential role in scheduling and planning.