Q. Hazard is defined as the probability of suffering harm or loss.
  • (A) true
  • (B) false
  • (C) topic 3.10 risk identification
  • (D) topic 3.9 critical path (crm) method
πŸ’¬ Discuss
βœ… Correct Answer: (B) false

Explanation: risk is the probability of suffering harm whereas hazard is a potential source of harm.


Explanation by: Mr. Dubey
risk is the probability of suffering harm whereas hazard is a potential source of harm.