Q. In bar charts, which colour is used to show the actual progress?
  • (A) red
  • (B) black
  • (C) blue
  • (D) green
πŸ’¬ Discuss
βœ… Correct Answer: (D) green

Explanation: in bar charts, different colours are sometimes filled in the bars for showing various control information. for actual progress, green colour is used. for anticipated


Explanation by: Mr. Dubey
in bar charts, different colours are sometimes filled in the bars for showing various control information. for actual progress, green colour is used. for anticipated