Q. A PERT network is activity-oriented while a CPM network is event-oriented.
  • (A) true
  • (B) false
  • (C) ---
  • (D) ---
πŸ’¬ Discuss
βœ… Correct Answer: (B) false

Explanation: a cpm network is activity- oriented while a pert network is event- oriented. event is the completion of an activity or the commencement of an activity. an event may be head event, tail event or dual role event.


Explanation by: Mr. Dubey
a cpm network is activity- oriented while a pert network is event- oriented. event is the completion of an activity or the commencement of an activity. an event may be head event, tail event or dual role event.