Correct Answer: (B)
optimistic time estimate
Explanation: there are three kinds of time estimates made by pert planners. these are the optimistic time estimate, the pessimistic time estimate and the most likely time estimate. the shortest possible time in which an activity can be achieved under ideal circumstances is known as the optimistic time estimate.
Explanation by: Mr. Dubey
there are three kinds of time estimates made by pert planners. these are the optimistic time estimate, the pessimistic time estimate and the most likely time estimate. the shortest possible time in which an activity can be achieved under ideal circumstances is known as the optimistic time estimate.