Q. SPMP stands for

  • (A) software project manager’s plan
  • (B) software project management plan
  • (C) software product management plan
  • (D) software product manager’s plan
πŸ’¬ Discuss
βœ… Correct Answer: (B) software project management plan
Explanation: after planning is complete, documenting of the plans is done in a software project management plan(spmp) document.

Explanation by: Mr. Dubey
after planning is complete, documenting of the plans is done in a software project management plan(spmp) document.