πŸ“Š Software Project Management (SPM)
Q. Which tender allows anyone to submit a tender to supply the goods or services that are required?
  • (A) framework tendering
  • (B) selective tendering
  • (C) open tendering
  • (D) close tendering
πŸ’¬ Discuss
βœ… Correct Answer: (C) open tendering

Explanation: on larger projects, there may then be a pre-qualification process that produces a short-list of suitable suppliers who will be invited to prepare tenders. this sort of pre-qualification process is not the same as selective tendering.


Explanation by: Mr. Dubey
on larger projects, there may then be a pre-qualification process that produces a short-list of suitable suppliers who will be invited to prepare tenders. this sort of pre-qualification process is not the same as selective tendering.

πŸ’¬ Discussion

πŸ“Š Question Analytics

πŸ‘οΈ
736
Total Visits
πŸ“½οΈ
2 y ago
Published
πŸŽ–οΈ
Mr. Dubey
Publisher
πŸ“ˆ
88%
Success Rate