Q. Choose the correct statement.
  • (A) CPM and PERT are event oriented techniques
  • (B) CPM and PERT are activity oriented techniques
  • (C) CPM is an activity oriented technique while PERT is an event oriented technique
  • (D) None of the above
πŸ’¬ Discuss
βœ… Correct Answer: (C) CPM is an activity oriented technique while PERT is an event oriented technique