πŸ“Š Industrial Engineering
Q. Which of the following statement regarding PERT is incorrect?
  • (A) It establishes the sequence and the relationship between significant programmes events
  • (B) It is statistical technique which makes decisions
  • (C) It points out slippages before the fact happens and its impact on others
  • (D) It helps to formulate new schedules when the existing schedule cannot be met.
πŸ’¬ Discuss
βœ… Correct Answer: (B) It is statistical technique which makes decisions