Q. By introducing a dummy activity in a network

  • (A) unique numbering system for different activities is maintained
  • (B) time is consumed additionally
  • (C) logical sequence of activities is disturbed
  • (D) Supply and demand conditions
πŸ’¬ Discuss
βœ… Correct Answer: (A) unique numbering system for different activities is maintained