πŸ“Š Power Plant Engineering (PPE)
Q. Size and cost of installation depends upon
  • (A) average load
  • (B) maximum demand
  • (C) square mean load
  • (D) square of peak load
πŸ’¬ Discuss
βœ… Correct Answer: (B) maximum demand

Explanation: the greatest of all “short time interval averaged” during a given period, on the power system is called the maximum demand. maximum demand represents the maximum amount of load that is active, out of total connected load. so the size and rating of power plant depends on maximum demand.


Explanation by: Mr. Dubey
the greatest of all “short time interval averaged” during a given period, on the power system is called the maximum demand. maximum demand represents the maximum amount of load that is active, out of total connected load. so the size and rating of power plant depends on maximum demand.