Q. Which of the following are not taken as operation and maintenance cost in economics of nuclear power plant?

  • (A) taxes and insurance
  • (B) salaries and wages of staff
  • (C) cost of waste disposal
  • (D) cost of processing materials
Share

Explanation by: Mr. Dubey
taxes and insurance are taken as fixed costs. salaries and wages of operation and maintenance staff, cost of waste disposal and cost of processing materials are the operation and maintenance cost.