Q. Estimating is the technique of calculating the various quantities and is needed for controlling the expenditure during the
  • (A) special data book
  • (B) standard data book
  • (C) special data record
  • (D) specific data record
πŸ’¬ Discuss
βœ… Correct Answer: (B) standard data book

Explanation: while fixing rate per unit of an item, the quantity of materials and labour needed for one unit of an item are strictly per the standard data book. however, the rates of labour and materials are obtained from the current standard scheduled of rates.


Explanation by: Mr. Dubey
while fixing rate per unit of an item, the quantity of materials and labour needed for one unit of an item are strictly per the standard data book. however, the rates of labour and materials are obtained from the current standard scheduled of rates.

πŸ’¬ Discussion

πŸ“Š Question Analytics

πŸ‘οΈ
1004
Total Visits
πŸ“½οΈ
2 y ago
Published
πŸŽ–οΈ
Mr. Dubey
Publisher
πŸ“ˆ
90%
Success Rate