πŸ“Š Construction Project Management
Q. Dummy activities are used to ?
  • (A) determine the critical path
  • (B) determine the project completion time
  • (C) maintain the required net work
  • (D) none of these
πŸ’¬ Discuss
βœ… Correct Answer: (C) maintain the required net work