M Mr. Dubey π Coach β 103.11K Points π Construction Management Q. A dummy activity (A) Is artificially introduced (B) Is represented by a dotted line (C) Does not consume time (D) All the above ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (D) All the above