Q. For excavating utility trenches with precise control of depth, the excavation equipment used is
  • (A) Hoe
  • (B) Shovel
  • (C) Dragline
  • (D) None of the above
πŸ’¬ Discuss
βœ… Correct Answer: (A) Hoe
πŸ“Š Construction Management
Q. The most popular type of organisation used for Civil Engineering Constructions, is
  • (A) Line organisation
  • (B) Line and staff organisation
  • (C) Functional organisation
  • (D) Effective organisation
πŸ’¬ Discuss
βœ… Correct Answer: (A) Line organisation
πŸ“Š Construction Management
Q. Pre-tender stage requires
  • (A) Acquisition of land
  • (B) Selection of site
  • (C) Fmalisation of alignment of work
  • (D) All the above
πŸ’¬ Discuss
βœ… Correct Answer: (D) All the above
πŸ“Š Construction Management
Q. An event is indicated on the network by a number enclosed in
  • (A) A circle
  • (B) A square
  • (C) A triangle
  • (D) All the above
πŸ’¬ Discuss
βœ… Correct Answer: (D) All the above
πŸ“Š Construction Management
Q. If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is
  • (A) (t1 - t2) - t
  • (B) t - (t1 - t2)
  • (C) (t1 + t2) - t
  • (D) t + (t1 - t2)
πŸ’¬ Discuss
βœ… Correct Answer: (A) (t1 - t2) - t
πŸ“Š Construction Management
Q. Free float for any activity is defined as the difference between
  • (A) Its earliest finish time and earliest start time for its successor activity
  • (B) Its latest start time and earliest start time
  • (C) Its latest finish time and earliest start time for its successor activity
  • (D) Its earliest finish time and latest start time for its successoractivity
πŸ’¬ Discuss
βœ… Correct Answer: (A) Its earliest finish time and earliest start time for its successor activity