πŸ“Š Construction Management
Q. If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
  • (A) (a + m + b)/6
  • (B) (a + 2m + b)/6
  • (C) (a + 4m + b)/6
  • (D) (a + 5m + b)/6
πŸ’¬ Discuss
βœ… Correct Answer: (C) (a + 4m + b)/6
πŸ“Š Construction Management
Q. Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth ofcut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimumdepth, (iv) Output can be increased by increasing the size of shovel. Of these statements
  • (A) (ii), (iii) and (iv) are correct
  • (B) (i), (ii) and (iv) are correct
  • (C) (i), (iii) and (iv) are correct
  • (D) (i) and (iv) are correct
πŸ’¬ Discuss
βœ… Correct Answer: (B) (i), (ii) and (iv) are correct
πŸ“Š Construction Management
Q. If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be
  • (A) to + 3tm+ tp/3
  • (B) to + 4tm+ tp/4
  • (C) to + 4tm+ tp/5
  • (D) to + 4tm+ tp/6
πŸ’¬ Discuss
βœ… Correct Answer: (D) to + 4tm+ tp/6
πŸ“Š Construction Management
Q. The most suitable type of equipment for compaction of cohesive soils is
  • (A) Smooth-wheeled rollers
  • (B) Vibratory rollers
  • (C) Sheep foot rollers
  • (D) Tampers
πŸ’¬ Discuss
βœ… Correct Answer: (C) Sheep foot rollers
πŸ“Š Construction Management
Q. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be
  • (A) Started 5 days later
  • (B) Completed 5 dayslater
  • (C) Performed at slower rate in 15days
  • (D) All the above
πŸ’¬ Discuss
βœ… Correct Answer: (D) All the above
πŸ“Š Construction Management
Q. Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions Of these statements
  • (A) Only (i) is correct
  • (B) (i) and (ii) are correct
  • (C) (i) and (iii) are correct
  • (D) (ii) and (iii) are correct
πŸ’¬ Discuss
βœ… Correct Answer: (C) (i) and (iii) are correct
πŸ“Š Construction Management
Q. A Milestone chart
  • (A) Shows the interdependencies of variousjobs
  • (B) Depicts the delay of jobs, if any
  • (C) Points outgoing ahead of schedule of jobs, if any
  • (D) None of these
πŸ’¬ Discuss
βœ… Correct Answer: (D) None of these
πŸ“Š Construction Management
Q. Earliest finish of an activity is always
  • (A) Greater than earliest event time of the following node
  • (B) Less than earliest event time of the following node
  • (C) Less than or equal to earliest event time of the following node
  • (D) Greater than or equal to earliest event time of the following node
πŸ’¬ Discuss
βœ… Correct Answer: (C) Less than or equal to earliest event time of the following node
πŸ“Š Construction Management
Q. If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be
  • (A) 50 %
  • (B) Less than 50 %
  • (C) More than 50 %
  • (D) 100 %
πŸ’¬ Discuss
βœ… Correct Answer: (C) More than 50 %