Q. A dummy activity
  • (A) Is artificially introduced
  • (B) Is represented by a dotted line
  • (C) Does not consume time
  • (D) All the above
πŸ’¬ Discuss
βœ… Correct Answer: (D) All the above
πŸ“Š Construction Management
Q. The reduction in project time normally results in
  • (A) Decreasing the direct cost and increasing indirect cost
  • (B) Increasing the direct cost and decreasing the indirect cost
  • (C) Increasing the direct cost and indirect cost both
  • (D) Decreasing the direct cost and indirect cost both
πŸ’¬ Discuss
βœ… Correct Answer: (B) Increasing the direct cost and decreasing the indirect cost
πŸ“Š Construction Management
Q. The area under the Beta distribution curve is divided into two equal parts by
  • (A) Most likely time
  • (B) Optimistic time
  • (C) Pessimistic time
  • (D) Expected time
πŸ’¬ Discuss
βœ… Correct Answer: (D) Expected time
πŸ“Š Construction Management
Q. CPM is
  • (A) Synthesising in concepts
  • (B) Is built of activities oriented programme
  • (C) Is based on time estimate
  • (D) All the above
πŸ’¬ Discuss
βœ… Correct Answer: (D) All the above
πŸ“Š Construction Management
Q. A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be
  • (A) 20 kg/tonne
  • (B) 30 kg/tonne
  • (C) 40 kg/tonne
  • (D) 50 kg/tonne
πŸ’¬ Discuss
βœ… Correct Answer: (C) 40 kg/tonne
πŸ“Š Construction Management
Q. The Overall in-charge of an organisation at the site responsible for the execution of the works, is
  • (A) Executive Engineer
  • (B) Engineer
  • (C) Junior Engineer
  • (D) Assistant Engineer
πŸ’¬ Discuss
βœ… Correct Answer: (B) Engineer
πŸ“Š Construction Management
Q. Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities ofproject PERT is preferred for planning becauseof
  • (A) 1, 2 and 4
  • (B) 3, 4 and 5
  • (C) 1, 3 and 4
  • (D) 1, 2 and 5
πŸ’¬ Discuss
βœ… Correct Answer: (A) 1, 2 and 4
πŸ“Š Construction Management
Q. The first stage of a construction, is
  • (A) Preparation of estimate
  • (B) Survey of the site
  • (C) Initiation of proposal
  • (D) Preparation of tender
πŸ’¬ Discuss
βœ… Correct Answer: (C) Initiation of proposal
πŸ“Š Construction Management
Q. Crash project duration is obtained by summing the
  • (A) Normal durations for all the activities
  • (B) Crash durations for all activities
  • (C) Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
  • (D) Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities.
πŸ’¬ Discuss
βœ… Correct Answer: (D) Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities.
πŸ“Š Construction Management
Q. Sinking fund is
  • (A) The fund for rebuilding a structure when its economic life is over
  • (B) Raised to meet maintenance costs
  • (C) The total sum to be paid to the municipal authorities by the tenants
  • (D) A part of the money kept in reserve for providing additional structures andstructural modifications
πŸ’¬ Discuss
βœ… Correct Answer: (A) The fund for rebuilding a structure when its economic life is over