Construction Management MCQs | Page - 12
Dear candidates you will find MCQ questions of Construction Management here. Learn these questions and prepare yourself for coming examinations and interviews. You can check the right answer of any question by clicking on any option or by clicking view answer button.
Q. The reduction in project time normally results in
β
Correct Answer: (B)
Increasing the direct cost and decreasing the indirect cost
Q. The area under the Beta distribution curve is divided into two equal parts by
β
Correct Answer: (D)
Expected time
Q. A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be
β
Correct Answer: (C)
40 kg/tonne
Q. The Overall in-charge of an organisation at the site responsible for the execution of the works, is
β
Correct Answer: (B)
Engineer
Q. Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities ofproject PERT is preferred for planning becauseof
β
Correct Answer: (A)
1, 2 and 4
Q. The first stage of a construction, is
β
Correct Answer: (C)
Initiation of proposal
Q. Crash project duration is obtained by summing the
β
Correct Answer: (D)
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities.
Q. Sinking fund is
β
Correct Answer: (A)
The fund for rebuilding a structure when its economic life is over
Jump to