Q. The chart which gives an estimate about the amount of materials handling between various work stations stations is known as ?
  • (A) flow chart
  • (B) time chart
  • (C) travel chart
  • (D) operation chart
πŸ’¬ Discuss
βœ… Correct Answer: (C) travel chart
πŸ“Š Construction Project Management
Q. The optimistic time represents ?
  • (A) shortest possible time in which an activity can be completed if everything goes exceptionally well
  • (B) time in which the activity is normally expected to complete under normal contingencis
  • (C) time in which an activity will take to complete in case of difficulty
  • (D) none of the above
πŸ’¬ Discuss
βœ… Correct Answer: (A) shortest possible time in which an activity can be completed if everything goes exceptionally well
πŸ“Š Construction Project Management
Q. In the critical path of construction planning, free float can be ?
  • (A) greater than total float
  • (B) equal to total float
  • (C) greater than independent float
  • (D) less than independent float
πŸ’¬ Discuss
βœ… Correct Answer: (C) greater than independent float
πŸ“Š Construction Project Management
Q. When float or slack of an activity is positive ?
  • (A) it represents a situation where extra resources are available and the completion of project is not delayed
  • (B) it represents that a programme falls behind schedule and additional resources are required to complete the project in time
  • (C) the activity is critical and any delay in its performance will delay the completion of whole project
  • (D) any one of the above
πŸ’¬ Discuss
βœ… Correct Answer: (A) it represents a situation where extra resources are available and the completion of project is not delayed
πŸ“Š Construction Project Management
Q. The time in which an activity will take to complete in case of difficulty, is called ?
  • (A) optimistic time
  • (B) most likely time
  • (C) pessimistic time
  • (D) none of these
πŸ’¬ Discuss
βœ… Correct Answer: (C) pessimistic time