πŸ“Š Software Project Management (SPM)
Q. Which of these are not among the eight principles followed by Software Engineering Code of Ethics and Professional Practice ?
  • (A) public
  • (B) profession
  • (C) product
  • (D) environment
πŸ’¬ Discuss
βœ… Correct Answer: (D) environment

Explanation: rest all are clauses for software ethics, environment does not focus on specific clause nor its of importace related to question.

πŸ“Š Software Project Management (SPM)
Q. Which of these does not account for software failure ?
  • (A) increasing demand
  • (B) low expectation
  • (C) increasing supply
  • (D) less reliable and expensive
πŸ’¬ Discuss
βœ… Correct Answer: (C) increasing supply

Explanation: increasing supply will lead to more production and not failure.

πŸ“Š Software Project Management (SPM)
Q. What are attributes of good software ?
  • (A) software maintainability
  • (B) software functionality
  • (C) software development
  • (D) software maintainability & functionality
πŸ’¬ Discuss
βœ… Correct Answer: (D) software maintainability & functionality

Explanation: good software should deliver the required functinality, maintainability.

πŸ“Š Software Project Management (SPM)
Q. Which of these is true ?
  • (A) generic products and customized products are types of software products
  • (B) generic products are produced by organization and sold to open market
  • (C) customized products are commissioned by particular customer
  • (D) all of the mentioned
πŸ’¬ Discuss
βœ… Correct Answer: (D) all of the mentioned

Explanation: all of them are true.

πŸ“Š Software Project Management (SPM)
Q. The fundamental notions of software engineering does not account for ?
  • (A) software processes
  • (B) software security
  • (C) software reuse
  • (D) software validation
πŸ’¬ Discuss
βœ… Correct Answer: (D) software validation

Explanation: software validation is an activity for software process and not the fundamental for engineering.

πŸ“Š Software Project Management (SPM)
Q. Which one of the following is not a software process quality?
  • (A) productivity
  • (B) portability
  • (C) timeliness
  • (D) visibility
πŸ’¬ Discuss
βœ… Correct Answer: (B) portability

Explanation: portability is a software product quality which means software can run on different hardware platforms or software environments.

πŸ“Š Software Project Management (SPM)
Q. & are two kinds of software products.
  • (A) cad, cam
  • (B) firmware, embedded
  • (C) generic, customised
  • (D) none of the mentioned
πŸ’¬ Discuss
βœ… Correct Answer: (C) generic, customised

Explanation: rest all are sub categories/applications of option c.

πŸ“Š Software Project Management (SPM)
Q. Software costs more to maintain than it does to develop.
  • (A) true
  • (B) false
  • (C) ---
  • (D) ---
πŸ’¬ Discuss
βœ… Correct Answer: (A) true

Explanation: for systems with a long life, maintenance costs may be several times development costs.

πŸ“Š Software Project Management (SPM)
Q. Which one of the following is not an application of embedded software product?
  • (A) keypad control of a security system
  • (B) pattern recognition game playing
  • (C) digital function of dashboard display in a car
  • (D) none of the mentioned
πŸ’¬ Discuss
βœ… Correct Answer: (B) pattern recognition game playing

Explanation: pattern recognition uses artificial intelligence (ai) software.

πŸ“Š Software Project Management (SPM)
Q. Purpose of process is to deliver software
  • (A) in time
  • (B) with acceptable quality
  • (C) that is cost efficient
  • (D) both in time & with acceptable quality
πŸ’¬ Discuss
βœ… Correct Answer: (D) both in time & with acceptable quality

Explanation: cost of a software is a management issue & is not related to process activities.