Q. Which of the following activities of a Generic Process framework provides a feedback report?
  • (A) communication
  • (B) planning
  • (C) modeling & construction
  • (D) deployment
πŸ’¬ Discuss
βœ… Correct Answer: (D) deployment

Explanation: in deployment the product is delivered to the customer who evaluates the product and provides feedback based on the evaluation.

πŸ“Š Software Project Management (SPM)
Q. Process adopted for one project is same as the process adopted from another project.
  • (A) true
  • (B) false
  • (C) ---
  • (D) ---
πŸ’¬ Discuss
βœ… Correct Answer: (B) false

Explanation: the overall flow of activities, actions,tasks,the level of autonomy given to the software team and the inter dependencies among two process can never be the same.

πŸ“Š Software Project Management (SPM)
Q. Which one of the following is not an Umbrella Activity that complements the five process framework activities and help team manage and control progress, quality, change, and risk.
  • (A) reusability management
  • (B) risk management
  • (C) measurement
  • (D) user reviews
πŸ’¬ Discuss
βœ… Correct Answer: (D) user reviews

Explanation: none.

πŸ“Š Software Project Management (SPM)
Q. Four types of change are encountered during the support phase.Which one of the following is not one that falls into such category?
  • (A) translation
  • (B) correction
  • (C) adaptation
  • (D) prevention
πŸ’¬ Discuss
βœ… Correct Answer: (A) translation

Explanation: translation is done in the development phase.

πŸ“Š Software Project Management (SPM)
Q. SCM stands for
  • (A) software control management
  • (B) software configuration management
  • (C) software concept management
  • (D) none of the mentioned
πŸ’¬ Discuss
βœ… Correct Answer: (B) software configuration management

Explanation: in software engineering, software configuration management (scm) is the task of tracking and controlling changes in the software, part of the larger cross- discipline field of configuration management.

πŸ“Š Software Project Management (SPM)
Q. When code is made available to others, it goes in a/an
  • (A) hard drive
  • (B) access-controlled library
  • (C) servers
  • (D) access control
πŸ’¬ Discuss
βœ… Correct Answer: (B) access-controlled library

Explanation: none.

πŸ“Š Software Project Management (SPM)
Q. Which of the following is not a main phase in Configuration Management (CM) Process?
  • (A) cm planning
  • (B) executing the cm process
  • (C) cm audits
  • (D) none of the mentioned
πŸ’¬ Discuss
βœ… Correct Answer: (D) none of the mentioned

Explanation: all are main phases of cm.

πŸ“Š Software Project Management (SPM)
Q. What allows different projects to use the same source files at the same time?
  • (A) version control
  • (B) access control
  • (C) cm process
  • (D) version control and access control
πŸ’¬ Discuss
βœ… Correct Answer: (A) version control

Explanation: it allows software engineers to continue development along a branch even when a line of development is frozen.

πŸ“Š Software Project Management (SPM)
Q. Which of the following is not a change management process?
  • (A) log the changes
  • (B) estimate impact on effort and schedule
  • (C) review impact with stakeholders
  • (D) none of the mentioned
πŸ’¬ Discuss
βœ… Correct Answer: (D) none of the mentioned

Explanation: all are required for a change.