πŸ“Š Cost and Works Accounting 1
Q. __________ is a written order directing the contractor to make changes according to the provisions of the contract documents.
  • (A) Change order / purchase order amendment
  • (B) Contract order modifications
  • (C) Contractor claim
  • (D) Owner directive
πŸ’¬ Discuss
βœ… Correct Answer: (A) Change order / purchase order amendment