Q. A cost unit is _____________
  • (A) a major of work output in a standard hour
  • (B) the cost per unit of electricity consumed
  • (C) a unit of product or service in relation to which costs are ascertained
  • (D) the costs per hour of operating a machine
πŸ’¬ Discuss
βœ… Correct Answer: (C) a unit of product or service in relation to which costs are ascertained