Q. What enables us to determine the earliest and latest times for each of the events and activities and thereby helps in the identification of the critical path?
  • (A) programme evaluation
  • (B) review technique (pert)
  • (C) both a and b
  • (D) deployment of resources
πŸ’¬ Discuss
βœ… Correct Answer: (C) both a and b