Q. …………….. is the provision to increase the contract price increase in the Cost of construction over a particular level
  • (A) Escalation clause
  • (B) Desecration clause
  • (C) Retention money
  • (D) work certified
πŸ’¬ Discuss
βœ… Correct Answer: (A) Escalation clause