Q. ……………is the duration by which an activity can be delayed without delaying the project
β
Correct Answer: (B)
total float
You must be Logged in to update hint/solution
Discussion
Question Analytics
742
Total Visits
2 y ago
Published
Priyanka Tomar
Publisher
93%
Success Rate