Q. ……… is the time by which the completion of an activity can be delayed beyond its earliest finish time without affecting the earliest start time of a succeeding activity
  • (A) slack
  • (B) total float
  • (C) free float
  • (D) independent float
πŸ’¬ Discuss
βœ… Correct Answer: (C) free float