Q. Which of the following best describes how short term schedules are prepared? short term schedules are prepared
  • (A) Directly from the aggregate plans
  • (B) Directly from the capacity plans
  • (C) From inventory records for items that have been used up
  • (D) From master schedules which are derived from aggregate plans
πŸ’¬ Discuss
βœ… Correct Answer: (D) From master schedules which are derived from aggregate plans