Q. The short term scheduling activity called loading
  • (A) Assign dates to specific jobs or operations steps
  • (B) Specifies the order in which jobs should be done at each center
  • (C) Assigns jobs to work centers
  • (D) Assign workers to jobs
πŸ’¬ Discuss
βœ… Correct Answer: (C) Assigns jobs to work centers