Q. In a PERT/CPM network, computing the critical path requires
  • (A) determining the total project duration
  • (B) assigning the earliest finish time for an activity as the earliest start time for the next
  • (C) that the latest finishing time for an activity not delay the overall project beyond initial expectation
  • (D) a sophisticated and complex computer program
πŸ’¬ Discuss
βœ… Correct Answer: (B) assigning the earliest finish time for an activity as the earliest start time for the next