Q. The latest finish time for an activity:
  • (A) Equals the min. of LFT − t for all immediate successors
  • (B) Equals the max. of LFT − t for all immediate predecessors.
  • (C) Equals the max. of EST + t for all immediate predecessors.
  • (D) Equals the min. of EST + t for all immediate successors.
πŸ’¬ Discuss
βœ… Correct Answer: (A) Equals the min. of LFT − t for all immediate successors