Q. Which of the following statements is true?
  • (A) PERT is considered as a deterministic approach and CPM is a probabilistic techniques.
  • (B) PERT is considered as a probabilistic techniques and CPM is considered as a deterministic approach.
  • (C) PERT and CPM are both probabilistic techniques.
  • (D) PERT and CPM are both considered as deterministic approachs.
πŸ’¬ Discuss
βœ… Correct Answer: (B) PERT is considered as a probabilistic techniques and CPM is considered as a deterministic approach.